Reports > September
 
 

Community Mitapheap II

 

located in Phum Mitapheap, Sangkat Russey Keo, Khan Russey Keo The construction of Drainage and Laterite road in community Mitapheap are completed 50% on Thursday 15 September 2005. Actual project cost at completion =US$ 4799.50

Project: Drainage and Laterite road (Constructing)
 
Community Prek Tanou3
 
Communnity Prek Tanou3 located in Krom 14,15, Phum Prek Tanou, Sangkat ChakAngre Leu, Khan Mean Chey The construction of drainage 174m x ø0.4m and Concrete lane 458.35m2 and soil filling 8 trucks in community Prek Tanou 3 are completed 100% . 20 September 2005. Actual project cost at completion =US$ 5393.40.
 

Before
 
After
Project: Drainage , Concrete lane and Soil filling (Completed: 20 Sept,2005)
 
Community Phleang Thleak
 
Community Phleang Thleak: located in Phum 3, Sangkat Boeung Kengkorg, Khan Chamkarmorn The construction of drainage 134m x ø0.4m and Concrete lane 405.79m2 . Project cost = US$ 4492.8 .
Project: Drainage and Concrete lane Prevented:
22 sept,2005
 
 