The Sen Monorom Park Project ( Former PTT Station )- Completed
Thursday, 02 Feb 2012 07:08
Officially Inaugurated on 2nd of February 2012
Project Information
Site Location: The intersection of Russian Blvd. and Monivong Blvd.
Project Owner: The Phnom Penh Capital Hall
Contractor: The Urbanization Officer of Urbanization Division
Start - To Complete: 05 May 2011 - 30 August 2011
Duration: 120 days
Budget: 447,172,440 Riels (111,793.11 USD)
Results: 100%
- Removed gas station and park size expasion: 100%
- Curb site of the park and side walk: 100%
- Soil covered to uplift level of park: 100%
- Tree planting: 8 : 100%
- Rain water drainage: 100%
- Installation of irrigation and electricity system within the park: 100%
- Grass and flower plantation: 100%
- Preah Kor Nes Stupa basement work: 100%
- Lighting Pole Installation within the park: 100%
- Pavement work along sidewalk: 100%
- Installation of sandstone tiles around the park: 100%
- Relocating of traffic signal: 100%
- However, in the middle of the park, the Preah Kor Nes Stupa standing and facing to the west
was being established on its basement with a dimension of 5m width and 7.2m height (from bottom of his head). This Stupa is being established actually in the site and expected to complete in the next 2 months.