The Sen Monorom Park Project ( Former PTT Station )- Completed
Thursday, 02 Feb 2012 07:08
Officially Inaugurated on 2nd of February 2012

Project Information

  • Site Location: The intersection of Russian Blvd. and Monivong Blvd.
  • Project Owner: The Phnom Penh Capital Hall
  • Contractor: The Urbanization Officer of Urbanization Division
  • Start - To Complete: 05 May 2011 - 30 August 2011
  • Duration: 120 days
  • Budget:​ 447,172,440 Riels (111,793.11 USD)
  • Results: 100%
  • - Removed gas station and park size expasion: 100%
    - Curb site of the park and side walk: 100%
    ​-​ Soil covered to uplift level of park: ​100%
    - Tree planting: 8 : 100%
    - Rain water drainage: 100%
    - Installation of irrigation and electricity system within the park: 100%
    - Grass and flower plantation: 100%
    - Preah Kor Nes Stupa basement work: 100%
    - Lighting Pole Installation within the park: 100%
    - Pavement work along sidewalk: 100%
    - Installation of sandstone tiles around the park: 100%
    - Relocating of traffic signal: 100%
    - However, in the middle of the park, the Preah Kor Nes Stupa standing and facing to the west
    was being established on its basement with a dimension of 5m width and 7.2m height (from bottom of his head). This Stupa is being established actually in the site and expected to complete in the next 2 months.